countyDutchess County Legislature
2024206
VILLAGE OF MILLERTON, AND TOWN OF NORTH EAST DUTCHESS COUNTY
- Introduced
- December 8, 2024
- Latest action
- December 8, 2024
- Status
- ADOPTED
- District coverage
- scope: countywide
Document text
Extracted from the official document; OCR may contain errors.
ENVIRONMENT
RE:
RESOLUTION NO. 2024206
DECLARING DUTCHESS COUNTY LEAD AGENCY AND
ADOPTION OF DETERMINATION OF NO SIGNIFICANT
ADVERSE ENVIRONMENTAL IMPACT IN CONNECTION
WITH DEPARTMENT OF PUBLIC WORKS COUNTY
ROUTE 62 (MAPLE AVENUE AND RUDD POND ROAD)
SIDEWALK IMPROVEMENT PROJECT, VILLAGE OF MILLERTON,
AND TOWN OF NORTH EAST DUTCHESS COUNTY
Legislators D'AQUANNI, TRUITT, HOUSTON, PAOLONI, and GORMAN offer the
following and move its adoption:
WHEREAS, the County is the owner of County Route 62 (Maple Avenue and Rudd Pond
Road) and is responsible for the maintenance and improvement of same; and
WHEREAS, the Department of Public Works ("DPW") has proposed a sidewalk
improvement project (the "Project") to replace existing sidewalks and add new sidewalks along
both sides of Maple Avenue and Rudd Pond Road (County Route 62) between Fish Street and
Highland Drive in the Village of Millerton and Town of North East, and
WHEREAS, the existing sidewalk network is in poor condition and lacks ADA compliant
curb ramps and widths, and
WHEREAS, in cooperation with its Consultant, DPW has prepared a Short Environmental
Assessment Form which documents that environmental issues have been investigated, and
WHEREAS, based on the foregoing, DPW has determined that the proposed project (1)
constitutes an Unlisted Action pursuant to Article 8 of the Environmental Conservation Law and
Part 617 of the NYCRR ("SEQRA"), and (2) will not result in any significant adverse
environmental impacts, and
WHEREAS, it is the purpose of the Legislature in adopting this resolution, to adopt and
confirm the above findings, and
WHEREAS, 6 NYCRR 617 requires the designation of a lead agency from among the
involved agencies before a determination of significance can be made, and
WHEREAS, DPW has circulated the proposed action to all involved agencies for thirty
days indicating its desire to be lead agency in accordance with 6 NYCRR 617.6 and no objection
was received, and it is the purpose of this resolution to establish Dutchess County as lead agency,
which will directly undertake and coordinate this Project pursuant to the New York State
Environmental Quality Review Act, and
WHEREAS, a copy of the Short Environmental Assessment Form and the finding that the
proposed action will not result in any significant adverse environmental impacts are annexed
hereto and made a part hereof, now, therefore, be it
RESOLVED, that Dutchess County hereby assumes lead agency status for this Project and
this Legislature hereby adopts and confirms the determination of the Dutchess County Department
of Public Works' consultant that the proposed Project entitled County Route 62 (Maple Avenue
and Rudd Pond Road) Sidewalk Improvement Project in the Village of Millerton and Town of
North East, Dutchess County, will not result in any significant adverse environmental impacts.
CA-130-24
AMS/mar/R-1079
10/29/24
Fiscal Impact: See Attached
APPROVEL
Lisan Serio
SUSAN J. SERINC
COUNTY EXECUTIVE
Deto 12/12/2024
STATE OF NEW YORK
SS:
COUNTY OF DUTCHESS
This is to certify that I, the undersigned Clerk of the I cgislature of the County of Dutchess, have compared the forgoing resolution with
the original resolution now on file in the office of said clerk, and which was adopted by said legislature on the 9%h day of December 2024, and that the
same is a true and correct transcript of said original resolution and of the whole thereof.
IN WITNESS WHEREOF, I have hercunto set my hand and scal of said I egislature this Ot day of December 2024
Righ Wager
NO FISCAL IMPACT PROJECTED
FISCAL IMPACT STATEMENT
APPROPRIATION RESOLUTIONS
(To be completed by requesting department)
Total Current Year Cost $
Total Current Year Revenue $
and Source
Source of County Funds (check one):
•Transfer of Existing Appropriations,
• Existing Appropriations,
•Contingency,
• Additional Appropriations, ZI Other (explain).
Identify Line Items(s):
Related Expenses: Amount $
Nature/Reason:
Anticipated Savings to County:
Net County Cost (this year):
Over Five Years:
Additional Comments/Explanation:
The Department is seeking the County to assume SEQR Lead Agency status for the environmental review of this
sidewalk improvement project along County Route 62 in the Town of North East. The Department is also seeking a the
Legislature's adoption of the Determination of No SignificantAdverse Environmental Impact.
Prepared by: Robert H. Balkind, P.E
Prepared On: 10/21/24
Dut pof
SUE SERINO
COUNTY EXECUTIVE
ROBERT H. BALKIND, P.E.
COMMISSIONER
DAVID C. WHALEN
DEPUTY COMMISSIONER
DUTCHESS COUNTY GOVERNMENT
DEPARTMENT OF PUBLIC WORKS
MEMORANDUM
TO:
FROM:
DATE:
R, Kashimer, Deputy County Executive
Robert H. Balind, PE, Commissioner ce te
October 21, 2024
SUBJECT:
Resolution Request - ADOPTION OF SEQR LEAD AGENCY AND
DETERMINATION OF NO SIGNIFICANT ADVERSE ENVIRONMENTAL
IMPACT FOR CR 62 SIDEWALK IMPROVEMENTS, TOWN OF NORTH
EAST, NY
DPW's Engineering Division has been working with a consultant to perform planning,
permitting and engineering design services, including development of bid documents for
a project to improve sidewalks and pedestrian access along County Route 62 (Maple Ave
and Rudd Pond Road) in the Village of Millerton and Town of North East.
SEQR Lead Agency notices were sent to interested and involved agencies on September
16, 2024, and no agency responded to challenge the County's intent to serve as Lead
Agency. In cooperation with the County's consultant, the Department prepared a Short
Form Environmental Assessment Form (SEAF) which documented potential
environmental impacts. The Department has concluded that the project will have No
Significant Adverse Environmental Impact. The SEQR Lead Agency Notice and SEAF are
attached to this memo.
The Department is seeking the Legislature's adoption of the County's Lead Agency
status, and to adopt the Determination of No significant Adverse Environmental Impact.
626 Dutchess Turnpike, Poughkeepsie, New York 12603 | (845) 486-2085 | Fax: (845) 486-2940
dutchessny.gov
SUE SERINO
COUNTY EXECUTIVE
ROBERT H. BALKIND, P.E.
COMMISSIONER
DAVID C. WHALEN
DEPUTY COMMISSIONER
DUTCHESS COUNTY GOVERNMENT
DEPARTMENT OF PUBLIC WORKS
MEMORANDUM
TO:
FROM:
DATE:
RE:
Robert H. Balkind, P.E., Commissioner
Mathew Dutcavich, P.E., Director of Engineering
October 16, 2024
RESOLUTION REQUEST: SEQRA LEAD AGENCY AND NEGATIVE DECLARATION FOR
THE COUNTY ROUTE 62 (MAPLE AVENUE) SIDEWALK IMPROVEMENT PROJECT,
VILLAGE OF MILLERTON
The Engineering Division has been advancing the design for a sidewalk improvement project
along CR 62 in the Village of Millerton. The project begins at Fish Street and continues north to
Highland Drive, improving approximately 2,000 linear feet of sidewalk.
The existing sidewalk network is in poor condition and lacks ADA compliant curb ramps and
widths. This project will address these deficiencies with widened sidewalks, new curb ramps, and
upgraded crosswalks, signs, and other ancillary work.
The project was determined to be an Unlisted Action pursuant to 617.6 of the State
Environmental Review Act (SEQRA). In accordance with the SEQRA, we issued a notice to
interested and involved agencies on September 16, 2024, of our conclusion that Dutchess County
should be designated lead agency for the subject project. No interested or involved agencies
responded otherwise. Additionally, we have determined that the project will not result in
significant adverse impacts and that a negative declaration should be made. With this memo,
please find:
• Lead Agency Designation Letter
Parts 1, and 2 of the Short Environmental Assessment Form (SEAF)
• Part 3 of the SEAF
A digital copy of the attachments as well as a draft Resolution Request Form and Fiscal Impact
Statement is available in the project folder on the server.
626 Dutchess Turnpike, Poughkeepsie, New York 12603 | (845) 486-2085
dutchessny.gov
County of Dutchess
NOTICE TO INTERESTED AGENCIES THAT
LEAD AGENCY MUST BE DESIGNATED WITHIN THIRTY (30) DAYS
COUNTY ROUTE 62 (MAPLE AVENUE) SIDEWALK IMPROVEMENT PROJECT
VILLAGE OF MILLERTON, TOWN OF NORTHEAST, DUTCHESS COUNTY, NY
Date: 9/16/2024
This Notice is issued pursuant to Part 617.6 of the implementing regulations pertaining to Article
8 (State Environmental Quality Review Act) of the Environmental Conservation Law to designate
a lead agency.
The action has been determined to be an Unlisted Action, pursuant to the
New York State Environmental Quality Review Act (SEQRA) 6 NYCRR Part 617. Dutchess County
has completed Part 1 of a Short Environment Assessment Form (SEAF), which has identified other
involved agencies for the action.
LEAD AGENCY DESIGNATION
Under the applicable standards of 6 NYCRR Part 617.6(b), the County of Dutchess concludes that
it should be designated as the lead agency in the coordinated environmental review of the action.
This notification is being sent to involved and/or interested agencies with the request that you
consent to the County of Dutchess serving as lead agency. If, however, you do not agree, you
may follow the procedures outlined in 6 NYCRR 617.6(b)(5).
This Notice is being transmitted on September 16, 2024. We ask that each agency that considers
themselves an involved or interested agency complete the annexed form and return it to the
contact person for receipt prior to the expiration of the required thirty-day notice period.
IF YOU DO NOT RESPOND WITHIN THIRTY (30) DAYS, IT WILL BE INTERPRETED AS CONSENT
THAT THE COUNTY OF DUTCHESS SERVE AS LEAD AGENCY. YOU WILL CONTINUE TO BE
NOTIFIED OF SEQR DETERMINATIONS AND ANY SUBSEQUENT PROCEEDINGS AND HEARINGS,
AS PROVIDED BY LAW.
LEAD AGENCY NOTICE
DATA SHEET
Name of Action:
COUNTY ROUTE 62 (MAPLE AVENUE) SIDEWALK IMPROVEMENT PROJECT
VILLAGE OF MILLERTON, TOWN OF NORTHEAST, DUTCHESS COUNTY, NY
Name of Applicant: Dutchess County Department of Public Works
SEQR Status:
X
Type I Action
_Unlisted Action
Description of Action: Dutchess County is proposing a project to perform ADA upgrades to
existing sidewalks along County Route 62 (Maple Avenue) in the Village of Millerton. The project
begins approximately 150 feet south of Park Street continuing north for approximately 2,000 feet
to Highland Drive in the Village of Millerton. The project involves replacement of approximately
2,000 feet of sidewalk on the western side of CR 62 and replacement with ADA compliant
sidewalk. The work includes the upgrade of the traffic signal at NYS Route 44 to include
pedestrian signals, and the installation of approximately 150 feet of new sidewalk along NYS
Route 44. The Short Environmental Assessment Form (SEAF), preliminary site plan and a location
map are being sent to all involved and interested agencies for review.
No significant environmental impact is anticipated from the proposed action.
Location of Action:
CR-62 Maple Avenue in the Village of Millerton
Tax Map No.(s):
Between Parcel Nos. 7271-18-467222 and 7271-00-515404
Size of parcel(s):
1.26 acres
Size of Action area:
0.85 acres
For further information, please contact:
Robert H. Balkind, P.E., Commissioner
Dutchess County Department of Public Works
626 Dutchess Turnpike
Poughkeepsie, NY 12603
Phone: (845) 486-2085
Email address: [email protected]
Thank you for your cooperation.
DATED:
September 16, 2024
ATTACHMENTS TO THIS NOTICE:
[X] Short Environmental Assessment Form (SEAF) Part 1
[X] Site Plan Map and Location Map
[X] Scope Summary Memorandum
A copy of this Notice is being sent to:
INTERESTED AGENCIES
Ms. Ruth L. Pierpont, Director
New York State Office of Parks, Recreation & Historic Preservation
Historic Preservation Field Services Bureau
Peebles Island, P.O. Box 189
Waterford, NY 12188-0189
Mr. Christopher Kennan, Supervisor
Town of Northeast
19 N. Maple Avenue
P.O. Box 516
Millerton, NY 12546
Mr. Peter Dellaghelfa, Superintendent of Public Works
Village of Millerton
5999 N. Elm Avenue
Millerton, NY 12546
Jennifer Najdek, Mayor
Village of Millerton
5933 N. Elm Avenue
Millerton, NY 12546
North East Fire District
Attn: Fire Chief
29 Century Boulevard
P.O. Box 653
Millerton, NY 12546
INVOLVED AGENCIES
William LaRose, Esq.
Field Permit Engineer
New York State Department of Transportation
334 Violet Avenue
Poughkeepsie, NY 12603
STATE OF NEW YORK
COUNTY OF DUTCHESS
Proposed Lead Agency:
Dutchess County Department of Public Works
Name of Action:
COUNTY ROUTE 62 (MAPLE AVENUE) SIDEWALK IMPROVEMENT PROJECT
VILLAGE OF MILLERTON, DUTCHESS COUNTY, NY
RESPONSE TO REQUEST THAT THE COUNTY OF DUTCHESS SERVE AS LEAD AGENCY
REGARDING THE ABOVE ACTION
On behalf of
Agency Notice in this matter.,
→ acknowledge receipt of the Lead
The above-named involved agency hereby:
[PLEASE CHECK ONE]
CONSENTS that the County of Dutchess serve as lead agency in this application and
requests that the undersigned continue to be notified of SEQR determinations,
proceedings and hearings in this matter.
DOES NOT CONSENT to the County of Dutchess serving as lead agency in this
application and wishes that
_ serve as lead agency. To contest lead
agency designation, the undersigned intends to follow the procedures outlined in 6
NYCRR 617.6(b)(5).
| 1 TAKES NO POSITION on Lead Agency designation.
Any agency raising a dispute must be ready to assume the lead agency if such agency
is designated by the commissioner per 6 NYCRR 617 (5) (1).
DATED:
. New York
By:
Agency Name
[signature]
[print signer's name]
Please return to:
Robert H. Balkind, P.E.
Dutchess County Department of Public Works
626 Dutchess Turnpike
Poughkeepsie, NY 12603
Short Environmental Assessment Form
Part 1 - Project Information
Lustructions for Completing
Part 1 - Project Information. The applicant or project sponsor is responsible for the completion of Part 1. Responses become part of the
application for approval or funding, are subject to public review, and may be subject to further verification. Complete Part I based on
information currently available. (fadditional research or investigation would be needed to fully respond to any item, please answer as
thoroughly as possible based on current information.
Complete all items in Part 1. You may also provide any additional information which you believe will be needed by or useful to the
lead agency; attach additional pages as necessary to supplement any item.
Part 1 - Project and Sponsor Information
Name of Action or Project:
Maple Avenue Sidewalk Improvements
Project Location (describe, and attach a location map):
Maple Avenue, Village of Millerton, Dutchess County, from 150 feet south of Park Street to Highland Drive
Brief Description of Proposed Action:
e proposed action includes the construction of ADA-compliant sidewalks along the west side of Maple Avenue beginning approximately150 fe
uth of Park Street to Highland Drive. A sidewalk will be installed along the northeast quadrant of the CR 62 and US 44 intersection, and a mid-blo
crossings it rese in eve i-conflat Sure a tops and rosess, Pedestin signals we installed i the new C2 and us to rossing at the
Name of Applicant or Sponsor:
Dutchess County Department of Public Works
Telephone: (845) 486-2925
E-Mail: [email protected]
Address:
DPW Engineering Division, 626 Dutchess Turnpike
City/PO:
State:
Poughkeepsie
New York
Zip Code:
12603
1. Does the proposed action only involve the legislative adoption of a plan, local law, ordinance,
NO
administrative rule, or regulation?
If Yes, attach a narrative description of the intent of the proposed action and the environmental resources that
may be affected in the municipality and proceed to Part 2. If no, continue to question 2.
2. Does the proposed action require a permit, approval or funding from any other government Agency?
NO
If Yes, list agency(s) name and permit or approval: NYSDOT- Highway Work permit
3.
a. Total acreage of the site of the proposed action?
b. Total acreage to be physically disturbed?
c. Total acreage (project site and any contiguous properties) owned
or controlled by the applicant or project sponsor?
1.26 acres
0.85 acres
0.92 acres
4. Check all land uses that occur on, are adjoining or near the proposed action:
5. Urban • Rural (non-agriculture) • Industrial
Commercial I Residential (suburban)
• Forest •
Agriculture
• Aquatic
Other (Specify):
• Parkland
YES
YES
Page 1 of 3
Is the proposed action,
a.
A permitted use under the zoning regulations?
b. Consistent with the adopted comprehensive plan?
6. Is the proposed action consistent with the predominant character of the existing built or natural landscape?
7. Is the site of the proposed action located in, or does it adjoin, a state listed Critical Environmental Area?
If Yes, identify:
NO
YES
N/A
NO
YES
NO
YES
8.
a.
Will the proposed action result in a substantial increase in traffic above present levels?
b. Are public transportation services available at or near the site of the proposed action?
c. Are any pedestrian accommodations or bicycle routes available on or near the site of the proposed
action?
9. Does the proposed action meet or exceed the state energy code requirements?
If the proposed action will exceed requirements, describe design features and technologies:
Not applicable.
NO
YES
NO
YES
V
10. Will the proposed action connect to an existing public/private water supply?
If No, describe method for providing potable water:
¡No new connections will be made to the existing watermains within the project area.
11. Will the proposed action connect to existing wastewater utilities?
If No, describe method for providing wastewater treatment:
No new connections will be made to the existing sanitary sewer within the project area.
2. a. Does the project site contain, or is it substantially contiguous to, a building, archaeological site, or distric
hich is listed on the National or State Register of Historic Places, or that has been determined by the
Commissioner of the NYS Office of Parks, Recreation and Historic Preservation to be eligible for listing on the
State Register of Historic Places?
Main St Historic District, see 8/21/24 OPRHP letter of No Effect
b. Is the project site, or any portion of it, located in or adjacent to an area designated as sensitive for
archaeological sites on the NY State Historic Preservation Office (SHPO) archaeological site inventory?
13. a. Does any portion of the site of the proposed action, or lands adjoining the proposed action, contain
wetlands or other waterbodies regulated by a federal, state or local agency?
b. Would the proposed action physically alter, or encroach into, any existing wetland or waterbody?
If Yes, identify the wetland or waterbody and extent of alterations in square feet or acres:
NO
YES
NO
YES
NO
•
YES
NO
YES
Page 2 of 3
14. Identify the typical habitat types that occur on, or are likely to be found on the project site. Check all that apply:
Shoreline
Forest LJ Agricultural/grasslands LI Early mid-successional
L Wetland
Urban Suburban
15. Does the site of the proposed action contain any species of animal, or associated habitats, listed by the State or
Federal government as threatened or endangered?
Northern Long-eared Bat, Se...
16. Is the project site located in the 100-year flood plan?
NO
YES
NO
YES
NO
YES
17. Will the proposed action create storm water discharge, either from point or non-point sources?
If Yes,
a. Will storm water discharges flow to adjacent properties?
b. Will storm water discharges be directed to established conveyance systems (runoff and storm drains)?
If Yes, briefly describe:
Sidewalks will be sloped towards Maple Avenue; runoff will be collected via storm drains and swales
18. Does the proposed action include construction or other activities that would result in the impoundment of water
or other liquids (e.g., retention pond, waste lagoon, dam)?
If Yes, explain the purpose and size of the impoundment:_
NO
YES
19. Has the site of the proposed action or an adjoining property been the location of an active or closed solid waste
management facility?
it Yes, describe:
NO
YES
20. Has the site of the proposed action or an adjoining property been the subject of remediation (ongoing or
completed) for hazardous waste?
If Yes, describe:
NO
YES
I CERTIFY THAT THE INFORMATION PROVIDED ABOVE IS TRUE AND ACCURATE TO THE BEST OF
MY KNOWLEDGE
Applicant/sponsor/name: Mathew D. Dutcavich, P.E.
signature: mat a lis
Date: 9-13-24
Title: Director, DPW Engineering Division
PRINT FORM
Page 3 of 3
Agency Use Only (If applicable)
Project:
Date:
Short Environmental Assessment Form
Part 2 - Impact Assessment
Part 2 is to be completed by the Lead Agency.
Answer all of the following questions in Part 2 using the information contained in Part 1 and other materials submitted by
the project sponsor or otherwise available to the reviewer. When answering the questions the reviewer should be guided by
the concept "Have my responses been reasonable considering the scale and context of the proposed action?"
No, or
small
impact
may
occur
Moderate
to large
impact
may
occur
T. Will the proposed action create a material conflict with an adopted land use plan or zoning
regulations?
2. Will the proposed action result in a change in the use or intensity of use of land?
3. Will the proposed action impair the character or quality of the existing community?
4. Will the proposed action have an impact on the environmental characteristics that caused the
establishment of a Critical Environmental Area (CEA)?
5. Will the proposed action result in an adverse change in the existing level of traffic or
affect existing infrastructure for mass transit, biking or walkway?
6. Will the proposed action cause an increase in the use of energy and it fails to incorporate
reasonably available energy conservation or renewable energy opportunities?
7. Will the proposed action impact existing:
a. public / private water supplies?
b. public / private wastewater treatment utilities?
8. Will the proposed action impair the character or quality of important historic, archaeological,
architectural or aesthetic resources?
• Will the proposed action result in an adverse change to natural resources (e.g., wetland
vaterbodies, groundwater, air quality, flora and fauna)
10. Will the proposed action result in an increase in the potential for erosion, flooding or drainage
problems?
11. Will the proposed action create a hazard to environmental resources or human health?
PRINT FORM
Page 1 of2
SEAF 2019
Project:
Date:
Short Environmental Assessment Form
Part 3 Determination of Significance
For every question in Part 2 that was answered "moderate to large impact may occur", or if there is a need to explain why a
particular element of the proposed action may or will not result in a significant adverse environmental impact, please
complete Part 3. Part 3 should, in sufficient detail, identify the impact, including any measures or design elements that
term, long-term and cumulative impacts.
Check this box if you have determined, based on the information and analysis above, and any supporting documentation,
that the proposed action may result in one or more potentially large or significant adverse impacts and an
environmental impact statement is required.
Check this box if you have determined, based on the information and analysis above, and any supporting documentation,
that the proposed action will not result in any significant adverse environmental impacts.
DUTCHESS COUNTY
8/30/24
Name of Lead Agency
Mathew D. Dutcavich, P.E.
Print or Type Name of Responsible Officer in Lead Agency
Tara
0. Curt
Signature of Responsible Officer in Lead Agency
Date
Director, DPW Engineering Division
Title of Responsible Officer
hiM. Willi
Signature of Preparer (if different from Responsible Officer)
PRINT FORM
Page 2 of 2
EAF Mapper Summary Report
Monday, December 12, 2022 7:59 AM
1:18-429240-0000-
7271:18-441236-00007271-18-472235
/7-221-16.4732 41 0007271-18-49239-0000
50007271 18-403239-0000
7271 18-458236-0000
7271-19-509241:0000)
7271-18:434223-0000
71-1 84912330000
7271/18-418227-0060~
7271-18-425223:0000
:7394-18-486224-0000
7271-18-467222-0000
7271-18-441218-00007271-18:45S2 10-0000
7271-18-433215-00007271-18-448220-0009
+7271-18-450209-0000
7271-18-498217-0000
Disclaimer: The EAF Mapper is à screening tool intended to assist
project sponsors and reviewing agencies in preparing an environmental
assessment form (EAF). Not all questions asked in the EAF are
answered by the EAF Mapper. Additional information on any EAF
question can be obtained by consulting the EAF Workbooks.
Although
the EAF Mapper provides the most up-to-date digital dala available to
DEC, you may also need to contact local or other data sources in order
to obtain data not provided by the Mapper. Digital data is not a
substitute for agency determinations.
Hurgo
Ctno Montea
Northeast
1274-18-4652 00-m0n0
1271-18-421199-0000
7271-18-432199-00007271-18-445197:00
1271-18-439197 00007271-18-451196-0000
7271-18-470194-0000
specs
7271:00-556143-0000
Toroeidu
tipaa oforhesy
Heu Vor
Hany
Detroit
Fish
S1
Cleveland
Boston
¿Providence
+ +271-18-490171-00007
Penns/onta
Ohe-
New York
nr OLIMPINERE MENTP NR P Eai Japan, METI, Essi Chiná (Hong Kong, Esri EMEN E*can Bsn Japan MET, Bhichta Hong Kong, Esn
Karea, 1rhala8Rocc, (d OpenStrea.maj ontributors, and the GiS User Community s([email protected] GIS User Comm unty
Part 1 / Question 7 [Critical Environmental
No
Area]
Part 1 / Question 12a [National or State
Yes
Register of Historic Places or State Eligible
Sites]
t 1 / Question 12b [Archeological Sites]
No
Part 1 / Question 13a [Wetlands or Other
Yes - Digital mapping information on local and federal wetlands and
Regulated Waterbodies]
waterbodies is known to be incomplete. Refer to EAF Workbook.
Part 1 / Question 15 [Threatened or
Yes
Endangered Animal]
Part 1 / Question 15 [Threatened or
Northern Long-eared Bat, Sedge Wren, Bog Turtle
Endangered Animal - Namel
Part 1 / Question 16 [100 Year Flood Plain] Yes
Part 1 / Question 20 [Remediation Site]
No
Chort Enuiranmantal Aannanmand Cumm
rAral_....r
May 2024
Design Memo
CR 62 Sidewalk Improvements
CHAPTER 1 - PROJECT INFORMATION
1.1 Project Limits
HIGHLAND DRIVE
SIDEWALK
IMPROVEMENT
PROJECT ENDS
TRAVER PLACE
BARTON STREET
SIMMONS STREET
PENUE (CR 02)
CENTURY BOULEVARD
MAIN STREET (US ROUTE 44)
PARK STREE
FISH STREET
SIDEWALK
IMPROVEMENT
PROJECT BEGINS
1.2
Project Purpose and Objectives
The purpose of this project is to improve pedestrian safety and mobility by providing sidewalk continuity on
the west side of Maple Avenue (CR 62) between Fish Street and Highland Drive, as well as provide
improvements at the intersection with Main Street (US Route 44). These improvements include the
replacement of existing sidewalks, the installation of new sidewalks, signage, and the installation of ADA-
compliant curb ramps and crosswalks.
1-1
May 2024
Design Memo
CR 62 Sidewalk Improvements
The project objectives are to improve pedestrian access and safety through an expanded accessible route
connecting residential housing, local businesses, and recreational areas.
1.3
Description of Proposed Work
The project includes the installation of approximately 1,950 LF of ADA-complaint sidewalks and pedestrian
curb ramps, signage as needed, and crosswalk striping along Maple Avenue (CR 62). The existing curb
along the west side of Maple Avenue will be left undisturbed, except in locations of curb ramps. The existing
closed drainage system will undergo slight modifications and relocations to correct existing drainage issues.
It is anticipated that no utility pole relocations will be required. The existing sidewalk at the southern end of
the project limits, as well as on intersecting roads, will be maintained and new sidewalk will be installed to
match the grade and width of the existing sidewalks.
Four alternatives have been considered for this project.
Alternatives Considered:
No Build (Null) Alternative: This alternative will maintain the existing condition and will not address the
concern of pedestrian access within the project limits. This alternative does not meet any of the project
objectives and is only used as a baseline for comparison to the other alternatives.
Alternative 1: This alternative proposes a continuous 5-foot-wide sidewalk along the west side of Maple
Avenue (CR 62) from the Kelsey Brook to Highland Drive. ADA-compliant curb ramps and crosswalks will
be installed at the intersections with Park Street, Main Street (US Route 44), Century Boulevard, Simmons
Street, Barton Street, and Highland Drive. Pedestrian signals with push buttons are proposed at the
intersection of Main Street (US Route 44) and Maple Avenue (CR 62) crossing south-north and west-east
near the Cumberland Farms. The sidewalk at Cumberland Farms extends to both driveways along Main
Street (US Route 44) and Maple Avenue (CR 62). Modifications to the existing drainage system along
Maple Avenue (CR 62) are anticipated. Curb extensions are proposed on Century Boulevard to shorten the
pedestrian crossing and delineate the parking areas.
Alternative 2: This alternative proposes the same improvements described in Alternative 1 with a crosswalk
and ADA-compliant curb ramps on the west side of the Maple Avenue (CR 62) and Main Street (US Route
44) intersection crossing south-north towards Cumberland Farms. One midblock crossing is proposed to
connect to the existing sidewalk on the east side of Maple Avenue near its intersection with Park Street.
Pedestrian signals with push buttons are proposed on the three (3) crosswalks at the Maple Avenue (CR
62) and Main Street (US Route 44) intersection. To enhance pedestrian safety at the midblock crossing,
rectangular rapid flashing beacon assemblies located at the crossings and advanced pedestrian warning
signage is proposed
Alternative 3: This alternative proposes the same improvements as described in Alternative 2 with the
removal of the midblock crossings, the curb extensions on Century Boulevard and the west-north crosswalk
and sidewalk and ADA-compliant curb ramps on the northeast corner of Main Street (US Route 44) and
Maple Avenue (CR 62). Pedestrian signals are proposed for the south-north crossing of Main Street (CR
62) and Maple Avenue (US Route 44). This alternative is not recommended because the removal of the
curb extensions would lengthen the pedestrian crossing, and removal of the midblock crossings does not
provide an accessible path for pedestrians within the project limits.
Alternative 4: This alternative proposes a continuous 5-foot-wide sidewalk along the west side of Maple
Avenue (CR 62) from the Kelsey Brook to Highland Drive. ADA-compliant curb ramps and crosswalks will
be installed at the intersections with Park Street, Main Street (US Route 44), Century Boulevard, Simmons
Street, Barton Street, and Highland Drive. Pedestrian signals with push buttons are proposed at the
1s a push uton are posed a
intersection of Main Street (US Route 44) and Maple Avenue (CR 62) crossing south-north and west-east
near the Cumberland Farms. The sidewalk at Cumberland Farms extends to both driveways along Main
Street (US Route 44) and Maple Avenue (CR 62). One midblock crossing is proposed to connect the
existing sidewalk on the east side of Maple Avenue near its intersection with Park Street. To enhance the
1-2
May 2024
Design Memo
CR 62 Sidewalk Improvements
safety at the midblock crossing, rectangular rapid flashing beacon assemblies located at the crossing and
advanced pedestrian warning signage are proposed. This alternative proposes the removal of existing
concrete stairs at the southeast corner of the intersection of Maple Avenue and Main Street, in front of the
North East Baptist Church, to deter pedestrians from crossing at this point.
Dutchess County has reviewed the alternatives and identified Alternative 4 as the preferred alternative.
1.4 Permits and Approvals
A NYSDOT Highway Work Permit is anticipated for this project for the work within the intersection of
Maple Avenue (CR 62) and Main Street (US Route 44).
1.5 Project Schedule
Activity
Scope Approval
Town and Public Meeting(s)
Design Approval
Pre-PS&E Submission
Right-of-Way Acquisition
PS&E Submission
Letting
Construction Start
Construction Complete
Note:
Project Schedule
Date Occurred/Tentative
June 2023
July - August 2023
May 2024
June 2024
Begin July 2024
December 2025
February 2025
April 2026
November 2026
Refer to Section 2.5 for a description of ROW needs for the preferred
alternative.
1.6
Public Involvement
A public information meeting was held on August 17, 2023 at the North East - Millerton Library to discuss
the project with residents and municipal officials. Refer to Appendix F for comments from this meeting.
1-3
May 2024
Design Memo
CR 62 Sidewalk Improvements
1.7
Project Cost
This project is 100% funded by Dutchess County.
Activity
Construction
Costs
Highway
Field Change Item
Mobilization (4%)
Subtotal
Contingency (30%)
Estimated Construction Cost
Project Gost
Alt. 1 Cost
$661,000
$34,000
$28,000
$723,000
$217,000
$940,000
Alt. 2 Cost
$665,000
$34,000
$28,000
$727,000
$219,000
$946,000
Alt. 3 Cost
$578,000
$29,000
$25,000
$632,000
$190,000
$822,000
Notes:
1. Project costs shown do not include costs for Design or Construction
Inspection.
2. Project costs shown do not include ROW acquisitions. Refer to Section
2.5 for a discussion on ROW needs.
Alt 4 Cost
$698,000
$35,000
$30,000
$763,000
$229,000
$992,000
1.8
Meeting Summaries
Site Visit
A site visit was conducted on August 25, 2022 to assess the existing conditions of the site. During this visit,
the County requested that there be no disturbance to overhead utilities or the State-owned traffic signal
located at the intersection of Maple Avenue (CR 62) and Main Street (US Route 44). A conceptual design
was submitted to the County for review and comment prior to submission of this Draft Design Memo. The
concept was reviewed with Dutchess County on December 21, 2022. The four alternatives presented in
this Draft Design Memo were developed at that meeting.
NYSDOT Review Meeting
Preliminary plans for the intersection of Maple Avenue (CR 62) and Main Street (US Route 44) were
provided to NYSDOT Region 8 for review in November 2023. On November 27, 2023, a design review
meeting was held virtually with NYSDOT, Dutchess County and MJ Engineering to discuss the proposed
work. NYSDOT was generally amenable to the pedestrian improvements shown but will require pedestrian
signals at the CR 62 / US 44 crosswalks. NYSDOT stated that the existing traffic signal cabinet could
accommodate the pedestrian phases. During final design, further review by the NYSDOT Region 8 Permits
group will follow the Highway Work Permit process. A permit will be issued before the project is advertised
1-4
May 2024
Design Memo
CR 62 Sidewalk Improvements
CHAPTER 2 - DESIGN CONSIDERATIONS
2.1
Design Criteria
Element
Curb Ramp Clear Width
Grade Running Slope
(for curb ramp)
Curb Ramp Cross Slope
Turning Space
(constraints at back)
Turning Space
(no constraints)
Slope of Turning Space
(any direction)
Sidewalk Clear Width
Sidewalk Grade Running
Slope
Sidewalk Cross Slope
Passing Space Interval
(if route is < 60" wide)
Passing Space
Dimensions
Crosswalk Width
Pedestrian Signal Push
Button Height
Ped. Signal Push Button
Dist. from Route
Primary Design Values for Sidewalks
Standard Value
Source!
48" (min.)
7.5% (max.)
PROWAG R304.5.1
PROWAG R304.3.2
1.5% (max.)
PROWAG R304.5.3
48" × 60"
PROWAG R304.2.1
48"x 48"
PROWAG R304.3.1
1.5% (max.)
48" (min.)
Adjacent Max. Roadway
Grade or 4.5%
1.5% (max.)
200' (max.)
PROWAG R304.2.2
PROWAG R304.3
PROWAG R304.2.5
PROWAG R304.2.6
PROWAG R304.2.4
60" × 60" (min.)
72" (min.)
36" (min.) - 42" (mаx.)
9" (max.)
PROWAG R304.2.4
PROWAG R304.2.3
PROWAG R406.2
PROWAG R406.3
Proposed Value
(Alt 4 - Preferred)
48" (min.)
7.5%
1.5%
48"× 60"
48' × 48"
1.5%
60"
Adjacent Roadway
Grade or
4.5%
1.5%
N/A
N/A
72"
36"- 42"
9" (max.)
NYSDOT Highway Design Manual Chapter 18 (2011 Public Right of Way Accessibility Guidelines
(PROWAG)).
2.2
Nonstandard/Nonconforming Features
There are no anticipated nonstandard features under this contract.
2.3
Safety and Crash History Analysis
Data from the CLEAR Crash Data Query report was reviewed for documented reports occurring between
May 2019 to May 2022 along Maple Avenue (CR 62) within and adjacent to the project limits. Of the thirteen
(13) accidents that occurred during this timeframe, none of the accidents reported involved pedestrians.
Refer to Appendix C for the NYSDMV Police Accident Reports.
2-1
May 2024
Design Memo
CR 62 Sidewalk Improvements
2.4
Pedestrians and Bicyclists
Pedestrians, Bicyclists and Transit (Complete Streets)
and commercial properties throughout the corridor. The intent of the project is to close the gaps in the
existing sidewalks and update existing pedestrian facilities to meet current ADA standards where required
along the west side of Maple Avenue (CR 62).
At the intersection of Maple Avenue (CR 62) with Main Street (US Route 44), pedestrian and bicycle counts
were recorded by the Dutchess County Transportation Council during the hours 7 am - 7 pm over a three-
day period from Thursday 5/4/23 to Saturday 5/6/23. From these counts, it was found that the predominant
pedestrian crossing movement at the intersection is in the east-west direction along Main Street. Refer to
Appendix E for the pedestrian and bicycle count data.
The Dutchess County Complete Streets Checklist has been completed. Refer to Appendix D for the
checklist.
Transit
There are currently no public transportation stops within the project limits. The proposed improvements will
not preclude future public transit bus stops within the project area.
2.5
Right-of-Way
The County's highway boundary has been mapped throughout the project limits, as shown on the
alternative plans in Appendix A.
Owner
Five Minute Construction Corp.
Victor C. Trivelli
Enver Cani
Enver Cani
Salisbury Bank and Trust Co.
CFI Propco 2 LLC
Anticipated Right-of-Way Acquisitions
Tax Map
Type of Acquisition
No.
Alt. 1
AlL. 2
Alt 3
Alt 4.
7271-18-467222
TE to remove existing sidewalk
7271-18-472235
TE to remove existing sidewalk
7271-14-477253
FEE to remove existing sidewalk, install new sidewalk,
and install pedestrian signal
7271-14-477253
TE to grade behind new sidewalk
FEE to
Grading
7271-14-483274
construct
-
release to
retaining wall-
replace
plantings
FEE to
7271-15-504270
FEE to construct sidewalk
construct
sidewalk
Total FEES
3
2
2
Total TEs
3
3
3
2-2
May 2024
Design Memo
CR 62 Sidewalk Improvements
2.6
Traffic Control Devices
There are eight (8) intersections within the project limits. The intersection of Maple Avenue (CR 62) and
Main Street (US Route 44) is controlled by an existing traffic signal, owned, and maintained by the New
York State Department of Transportation (NYSDOT), with no pedestrian signal equipment. No physical
modifications to this signal are proposed; however, the addition of new pedestrian signals will require
modifications in the cabinet. The other seven (7) intersections are stop controlled on the minor approaches
only.
2.7
Drainage Systems and Stormwater Management
There are existing closed drainage systems located within the project limits. Modifications to these systems
are proposed at the intersections of Maple Avenue (CR 62) and Park Street, Main Street (US Route 44),
and Century Boulevard.
2.8
Utilities
Utilities
Utility
Village of Millerton Water
Village of Millerton Drainage
Overhead Utilites (Electric,
Telephone, and Communication)
Impact
Two (2) hydrants to be relocated along the section of Maple
Avenue between Barton Street and Highland Drive. Alternative 2
includes an additional hydrant relocation along Park Street. Valve
Box adjustments will also be required and will be completed by the
Contractor. Coordination with the Village's water department to
obtain record plans of the existing infrastructure is ongoing.
Drainage alterations are anticipated at the three (3) intersections
identified in Section 2.7. Concept level modifications are shown in
Appendix A
No anticipated impact.
2.9
Work Zone Safety and Mobility
Work zone traffic control staging will be utilized during construction to complete earthwork,
installation, curb installation, and installation of pedestrian crosswalks. The staging includes but is not
Access for emergency vehicles will be open and maintained at all times during construction. A detailed
work zone traffic control plan will be designed and evaluated during final design.
Access to the businesses and private residences shall remain open at all times.
2-3
May 2024
Design Memo
CR 62 Sidewalk Improvements
CHAPTER 3 - ENVIRONMENTAL CONSIDERATIONS
3.1
Environmental Classification
SEQRA (State Environmental Quality Review Act):
In accordance with 6 NYCRR Part 617, "Procedures for Implementation of State Environmental Quality
Review Act", Dutchess County has determined that this project is a SEQR Unlisted Action since the project
proposed is to replace existing sidewalk and construct new sidewalk.
For Unlisted SEQRA actions, the need to undergo a coordinated SEQRA review, when there is more than
ne agency involvea
Short Environmental Assessment Form.
3.2 Historic and Cultural Resources
A review of the NYs Office of Parka, Recreation and Historical Preservation's (OPHP) Cultural Resource
Information System (CRIS) shows that the southern leg of the intersection of Maple Avenue (CR 62) and
Main Street (US Route 44) is located within the Main Street Historic District.
Three (3) historic properties listed on the National Register of Historic Places have been identified within or
immediately adjacent the project limits; 4 South Maple Avenue, the North East Baptist Church Parsonage
located at 3 South Maple Avenue, and the North East Baptist Church located at 1 South Maple Avenue. All
project activities take place within the public right-of-way and will not have any effects on these historic
properties. Refer to Appendix B for the CRIS map.
3.3 Surface Waterbodies and Watercourses
Based on a review of the NYSEC Environmental Resource Mapper (ERM), there is one (1) regulated
stream, Kelsey Brook, within the project limits. Kelsey Brook is rated a Class C / Standard C stream and is
not listed as a 303(d) segment. No impacts to Kelsey Brook are anticipated from the project activities.
3.4 Endangered and Threatened Species
A review of the NYSDEC ERM indicates that the NYSDEC's Natural Heritage Program has records of state-
listed endangered or threatened bat species that have the potential to exist within or near the project
corridor.
Northern Long Eared Bat
The Northern Long Eared Bat (NLEB) (Myotis septentrionalis) was identified as an endangered species
that has the potential to occur at the project site. The habitat provided within the project area is urban in
nature and provides minimal tree cover, vegetation or other characteristics typically associated with bal
habitats. A total of 12 trees will be cleared during construction and will be removed within the cutting window,
between November 1 and March 31. The canopy cover lost as a result of these tree removals is negligible
in comparison to the surrounding area.
Indiana Bat
The Indiana Bat (Myotis sodalis) was identified as an endangered species that has the potential to occur at
the project site. The habitat provided within the project area is urban in nature and provides minimal tree
cover, vegetation or other characteristics typically associated with bat habitats. A total of 12 trees will be
3-1
May 2024
Design Memo
CR 62 Sidewalk Improvements
cleared during construction and will be removed within the cutting window, between November 1 and March
31. The canopy cover lost as a result of these tree removals is negligible in comparison to the surrounding
area.
3.5
Floodplains
As indicated by FEMA on available GIS floodplain mapping, approximately 360 SF of the project area is
located in flood zone "AE", a 100-year floodplain that faces the risk of flooding up to a given base flood
elevation. The regulatory waterway, Kelsey Brook, passes under Maple Avenue between Fish Street and
Park Street. Due to the scope of work in this area of the project limits, no adverse effects or changes to the
existing flood zone from project activities are foreseen. Refer to Appendix B for the FEMA flood map of
this location.
3.6 Energy Code Requirements
This project is not applicable to the 2020 Energy Conservation Construction Code.
3.7
Stormwater Management
This project will disturb less than one acre and will not require a State Pollutant Discharge Elimination
ystem (SPDES) permit. While this project is not required to assess the requirements for stormwate
nanagement practices, they will be considered where reasonable. Contract documents will include erosio
and sediment control measures in accordance with the NYSDEC's Standards and Specifications for Erosion
and Sediment Control (latest edition) and Section 209 of the NYSDOT Standard Specifications.
3-2
Project Approval Sheet
The required environmental determinations have been made, and the preferred alternative for this project
is ready for final design. There are no nonstandard features for this project.
Michael D. Panichelli, PE directly supervised the preparation of the Design Memo is accordance with
established standards, policies, regulation, and procedure, except as otherwise explained in this
05.28.2024
Date
Michael D. Panichelli, PE
MJ Engineering & Land Surveying, P.C.
The included Design Memo has been reviewed and approved.
Mate C. Date
Mathew Dutcavich, PE
5-22-24
Date
Director of Engineering
enfed in this Design Memo is approved and ready for final design.
5/2644
Commissioner of Public Works
Environment Committee Roll Call
District
District 7 - Hyde Park and Pleasant Valley
District 25 - Amenia, Washington, Pleasant Valley & Millbrook
District 3 - LaGrange
District 16 - Fishkill and Beacon
District 9 - City of Poughkeepsie
District 1 - Town of Poughkeepsie
District 4 - Hyde Park and Town of Poughkeepsie
District 5 - Town of Poughkeepsie
District 6 - Town of Poughkeepsie
District 13 - East Fishkill and Wappinger
District 18 - City of Beacon and Fishkill
District 24 - Dover and Pawling
Present:
Absent:
Vacant:
I
Resolution:
Motion:
Name
Truitt*
Houston*
Polasek*
Valdés Smith*
Atkins*
Gorman
Lawler
D'Aquanni (C)
Kaul
Paoloni (VC)
Page
House
Total :
Abstentions:
Yes
No
Absent
11
Yes
0
No
2024206 DECLARING DUTCHESS COUNTY LEAD AGENCY AND ADOPTION OF
DETERMINATION OF NO SIGNIFICANT ADVERSE ENVIRONMENTAL IMPACT IN
CONNECTION WITH DEPARTMENT OF PUBLIC WORKS COUNTY ROUTE 62 (MAPLE
AVENUE AND RUDD POND ROAD) SIDEWALK IMPROVEMENT PROJECT, VILLAGE
OF MILLERTON, AND TOWN OF NORTH EAST DUTCHESS COUNTY
DECEMBER 5, 2024
Roll Call Sheets
District
Present:
Absent:
Vacant:
Last Name
District 7 - Hyde Park and Pleasant Valley
District 25 - Amenia, Washington, Pleasant Valley & Millbrook
District 3 - LaGrange
District 16 - Fishkill and Beacon
District 9 - City of Poughkeepsie
District 1 - Town of Poughkeepsie
District 2 - LaGrange, Pleasant Valley & Town of Poughkeepsie
District 4 - Hyde Park and Town of Poughkeepsie
District 5 - Town of Poughkeepsie
District 6 - Town of Poughkeepsie
District 8 - City and Town of Poughkeepsie
District 10 - City of Poughkeepsie
District 11 - Clinton, Pleasant Valley, and Rhinebeck
District 12 - East Fishkill
District 13 - East Fishkill and Wappinger
District 14 - Wappinger and Town of Poughkeepsie
District 15 - Wappinger
District 17 - Town and Village of Fishkill
District 18 - City of Beacon and Fishkill
District 19 - North East, Stanford, Pine Plains, Milan & Red Hook
District 20 - Red Hook, Tivoli, and Rhinebeck
District 21 - East Fishkill
District 22 - Beekman and Union Vale
District 23 - Pawling, Beekman and East Fishkill
Truitt
Houston
Polasek
Valdés Smith
Atkins
Gorman
Travelpiece
Lawler
D'Aquanni
Kaul
Brendli
Johnson
Kearney
Metzger
Paoloni
Versaci
Faust
McHoul
Page
Drago
Munn
Caswell
Garito
Rolison
Resolution: _
Datia 21. Doveyand Paving Hous
House
Total:
Motion:
Abstentions:
NO
25
Yes
No
2024206 DECLARING DUTCHESS COUNTY LEAD AGENCY AND ADOPTION OF
DETERMINATION OF NO SIGNIFICANT ADVERSE ENVIRONMENTAL IMPACT IN
CONNECTION WITH DEPARTMENT OF PUBLIC WORKS COUNTY ROUTE 62 (MAPLE
AVENUE AND RUDD POND ROAD) SIDEWALK IMPROVEMENT PROJECT, VILLAGE
OF MILLERTON, AND TOWN OF NORTH EAST DUTCHESS COUNTY